Step 3: Installing Additional Layers of Sing Logs

With the first layer done…

Place the logs for the second course parallel to their intended locations around the perimeter. Keep in mind again that just as the corners alternate with each layer, so should the butt joint seams. Align double tongue-and-groove joints, and squeeze a minimum of two (amounts vary according to log size & engineering conditions) thick beads of adhesive onto the top face of the log (outside of tongue) upon which you will install the first log of the second course. You should have at least one bead on both sides of the hollow space. Make sure that there is enough glue to squash down and form a tight seal when you place the next log on top. If you are using the recommended Franklin Titebond adhesive, keep in mind that in wet weather it may not fully cure for possibly 2 weeks because it’s water based, however it is very user health friendly and the screws pin the logs in place until the glue is cured. Make sure that the tongue on the bottom log is aligned correctly with the groove of the top log. If you find the tongues and grooves are fitting a little too snug, simply use a mallet and a piece of wood blocking to tamp them into place.

Sing Log Home - How to build Sing Log Home - How to build Sing Log Home - How to build

Drive an Olyscrew through a pre-drilled hole. It doesn’t matter which of the two wall sides you begin on, just make sure the screw is driven straight down to ensure solid contact is made all the way through the log. Be sure that it doesn’t hit the tie down plate or another screw below it. If at any time the screw threads or part of screw is exposed back it out and try again. No part of the screw should be visible (check the inside of the log to be certain the screw hasn’t gone through the curved part and is showing). Drive the screw until its head is countersunk and flush with the surface. Don’t be alarmed if the log rises further down its length, you will correct it when you drive the next screws. Be aw a leveling device, backing it out or driving it in tighter until its level. Avoid driving the screws into knots. After you gain a sense for the procedure and how it should look, you can are that the screws may alter the leveling somewhat, but you can actually employ the screw check for plumb and level every 2 or 3 layers.

Go to Step 4 –>

 

Leave a Reply

Your email address will not be published. Required fields are marked *